Project meeting #17 on site today in Larvik. Construction is progressing according to plan. Prefab steel columns we being welded and precast slabs lowered into place on the second floor. Masons have also started laying insulated CMU blocks around the foundataion perimeter where the terrain meets the facade. The superstructure continues to grow at a rate of about a floor every two weeks, so it won't be long now before we can see the outline and structure of the whole school.

New photos of the site were taken In between detail meetings and bouts of rain. Check the Mesterfjellet Construction Photos gallery for more.